Search Documents

Sort by

  • AIME
    Stope Blasting Design and Experience at the Carr Fork Mine

    By Dan Crackel, G. G. Ramos, Mark Heisel

    INTRODUCTION Feasibility studies indicated that a cratering type stoping method was best suited to the character of the first ore block at Carr Fork. This method known as vertical crater retreat (

    Jan 1, 1981

  • AUSIMM
    Stope Cleaning - Historical Methods

    In classical drill and blast underground mining methods, especially narrow vein operations economic quantities of broken ore can be left behind following normal mucking operations on the stope floors.

    Aug 1, 2010

  • AUSIMM
    Stope Control at The C.S.A. Mine, Cobar

    Stope control information at the C.S.A. mine is obtained by diamond drilling inclined holes from within the stapes. Practical mining outlines are determined from complicated ore contours by a joint mi

    Jan 1, 1969

  • AIME
    Stope Cost Records And Mine Contracts Of The Anaconda Copper Mining Co.

    By C. L. Berrien

    BEFORE the present company was formed, in 1916, each group of mines comprising the old organizations made its detailed daily and monthly mine cost records along the lines used before the consolidation

    Jan 2, 1922

  • SAIMM
    Stope deformation measurements as a diagnostic measure of rock behaviour: a decade of research - Synopsis

    By D. F. Malan

    This paper presents an overview of work conducted over several years to investigate the continuous stope closure profiles recorded in tabular excavations and the use of this data as a hazard indicator

    Jan 1, 2007

  • AUSIMM
    Stope Design Based on Realistic Joint Networks

    By J Hadjigeorgiou

    The stability of open stopes in underground hard rock mines is influenced by several factors including the shape and size of the excavation, surrounding stresses as well as the degree of jointing. Thi

    Jan 1, 2000

  • NIOSH
    Stope Design Considerations Using Rock Mass Classification Tools At The Xstrata Zinc George Fisher Mine

    By Jeremy P. Doolan, Leigh B. Neindorf, Geoff W. Capes

    The development and use of rock mass classification tools have been a key component for improving stope design over the past 4 years at the Xstrata Zinc George Fisher Mine in northern Queensland, Aust

    Jan 5, 2007

  • SAIMM
    Stope design in the Hishikari Gold Mine, Japan, by using numerical analysis

    By Y. Sagawa

    The Hishikari Gold Mine consists of epithermal vein type Au-Ag deposits, each of which has several veins standing almost in parallel each other and inclining 70 to 90 degrees. The veins have 1 to 3m w

    Jan 1, 2003

  • AUSIMM
    Stope Design Within a Final Pillar Retreat Sequence at Xstrata Copper's Mount Isa Copper Mines

    Xstrata CopperÆs Mount Isa Copper Operations is located in mineral rich north-west Queensland and is one of the largest sources of copper in the world. This world-class underground operation is planne

    Jan 1, 2007

  • CIM
    Stope development for raise mining at the Namew Lake mine

    By D. Madsen, B. Salamondra, A. Moss, D. Etienne

    "Raise mining at the Namew Lake Nickel Mine in Manitoba uses 3 m diameter bored raises driven at 45 to 50 degrees dip for stope access and drilling. These raises are developed within the orebody on 20

    Jan 1, 1991

  • AUSIMM
    Stope Filling At Boulder Perseverance Shaft 1895-1972

    A short study showing how first dry fill and later hydraulic sand fill has allowed mining to continue immediately adjacent to worked out areas in a mine 75 years old. This paper is a case study of

    Jan 1, 1973

  • AUSIMM
    Stope Filling at North Mount Lyell Mine

    IN the irregularly shaped ore-bodies of the North Mount Lyell mine by overhead stoping, the method of filling the is a special feature.The situation of the mine two miles from the smelter and mill at

    Jan 1, 1927

  • AUSIMM
    Stope Filling at the North Mine, Broken Hill

    North Broken Hill Limited came into prominence as a producing mine at· the commencement of the present century, when a great many of the disabilities experienced in earlier mining operations th:r

    Jan 1, 1940

  • CIM
    Stope Filling at the Sullivan and Other Canadian Mines

    By James D. Hall

    THIS essay deals with the materials and methods used in the waste filling of scopes in Canadian mines, with especial reference co the methods used at the Sullivan mine, Kimberley, B.C. The author wo

    Jan 1, 1937

  • AUSIMM
    Stope Filling with Thickened Classified Flotation Tailings

    By Yates C, Gillie E. W, Finucane K. J

    During the year 1940 a complete investigation was made of the whole of the stoping operations throughout the Great Boulder Mine and, as a result, it was decided to convert some of the existing shrinka

    Jan 1, 1945

  • AUSIMM
    Stope Filling with Thickened Classified Flotation Tailings (8ea60644-b41a-4846-93fc-367236e8ddfb)

    Stope filling practice on the Great Boulder Mine was described in -a paper published in Aus.I.M.M., Proceedings No. 137, in 1945. When the paper was presented the process had emerged from the experime

    Jan 1, 1948

  • AIME
    Stope in Malagash Salt Mine, Nova Scotia

    By AIME AIME

    THE two illustrations below, furnished through the courtesy of J. P. Messervey, Deputy Inspector of Mines, Department of Public Works and Mines, Province of Nova Scotia, show a fourth-level stope in t

    Jan 1, 1932

  • AUSIMM
    Stope Optimisation Tools for Selection of Optimum Cut-Off Grade in Underground Mine Design

    By B Hall

    In feasibility studies the choice of optimum cut-off grade is typically based on an evaluation of tonnage grade curves and manual design of stopes at one or two cut-off grades. In the industry these s

    Jan 1, 2009

  • AUSIMM
    Stope Performance at Olympic Dam Mine

    By M J. Pascoe

    The performance of 460 stope surfaces at WMC ResourcesÆ Olympic Dam Operation (ODO) has been used to investigate the confidence that can be placed in the Stability Graph Method for design of stope dim

    Jan 1, 2005

  • AUSIMM
    Stope Performance in Challenging Ground Conditions: Observed Versus Predicted - A Case Study

    Throughout the study phases (scoping, prefeasibility and feasibility) of new mining projects one is forced to work with and make predictions based upon limited date obtained from diamond and reverse c

    Nov 25, 2010