Helical Piers/ Anchors in the Chicago Building CodeBy Gary L. Seider, Dana A. Wesolek, Fred C. Schmednecht
"A new condominium project, The Atelier, developed by Pickus Companies located at the corner of Bryn Mawr and Sheridan in Chicago, IL required an earth retention system to protect the surrounding road
Jan 1, 2005
-
SIMBAT Dynamic Pile Testing - Results of an Independent Pile Capacity' Prediction EventBy Richard T. Stain
"In 2001, a pile trial site was established at Limelette in Belgium consisting of 25 displacement screw piles and 5 driven pre-cast piles. Interested parties were invited to participate in a pile pred
Jan 1, 2005
-
A Case Study Of A Vibratory Pile Installation Monitoring Of A Precast Prestressed Concrete PileBy K. Viking
It's well known that conventional impact hammers, usually are the method to use in order to drive precast prestressed concrete piles. However sometimes the vibratory technique might be considered
Jan 1, 2004
-
Behavior Of Large Bored Piles With Grouted EndBy Zhang Yaonian
This paper describes full-scale tests on ten large bored piles with grouted end conducted for three projects in the urban area of Fuzhou city. Test program included site investigation, pile installati
Jan 1, 2004
-
Design, Prediction And Performance Of Tied Back Shotcrete Walls Supporting Masonry Hospital StructuresBy Frank Borda
Two recent projects were completed in Ontario, Canada for major hospital additions that involved excavation support of heritage masonry structures. Conventional continuous caisson wall schemes were re
Jan 1, 2004
-
Approach To Reliability Based Design On Deep Mixing Improved GroundBy Masaki Kitazume
Deep mixing method, in-situ admixture stabilization technique, has been developed and adopted for on land and marine construction works in Japan. The geotechnical design procedure of the method has be
Jan 1, 2004
-
Design And Construction Of Integral Drilled Shaft - Columns For The Boscawen-Canterbury BridgeBy Frederick C. Rhyner
Drilled shafts have become an economical foundation choice for bridges in the northeast United States, especially when they can be constructed over water without the use of cofferdams. For the Boscaw
Jan 1, 2004
-
PVC And Steel Access Tube Debonding During Sonic Logging Testing For The SC 170 Bridge Replacement ProjectBy Edward L. Hajduk
During sonic logging quality control testing of the drilled shaft foundations for the replacement bridges crossing the Broad and Chechessee Rivers for SC 170 in Beaufort County, South Carolina, irregu
Jan 1, 2004
-
Laterally Loaded Model Piles In Jointed Soft Rock MassesBy B. Francis
Literature provides only limited information regarding the behaviour of laterally loaded piles socketed into weak rock masses. A laboratory program, comprising a number of tests of scaled models of th
Jan 1, 2004
-
PSEG Lawrenceburg Energy Facility Augered Cast -In-Place Piles Case HistoryBy Chris D. Shewmaker
So you want to install 2,600 augered cast-in-place piles, about 155,000 lineal feet, in 33 working days? It can be done. The Public Service Enterprise Group (PSEG) decided to build a combined cycle po
Jan 1, 2004
-
New Developments of Jacked PilesBy Victor Li, Joley Lam
"INTRODUCTIONJacked piles are piles that are pressed into the ground, usually by hydraulic jacks. For this reason, jacked piles are also known as pressed in piles. Jacked piles are mainly used for the
Jan 1, 2004
-
Augered Cast-In-Place (ACIP) And Drilled Displacement (DD) Pile Quality Control ? IntroductionBy Rudolph P. Frizzi
Quality control is essential for augered cast-in-place (ACIP) piles (also known as continuous flight auger (CFA) piles outside the United States) and drilled displacement (DD) piles since the pile is
Jan 1, 2004
-
Application Of Augered, Cast-In-Place Displacement (ACIPD) Piles In New York CityBy Willie M. NeSmith
Conventional augered, cast-in-place (ACIP) piles were introduced into the New York City area as a result of the damage to existing structures caused by pile driving operations. ACIP piles are often sp
Jan 1, 2004
-
Selection & Design Of Augered Cast-In-Place (ACIP) PilesBy Dan A. Brown
Outline ? Basic Concept of ACIP Piles ? Factors Affecting ACIP Pile Performance ? Applications: - Favorable Conditions - Unfavorable Conditions ? Design for Axial Loading ? Lateral Loa
Jan 1, 2004
-
New Tacoma Narrows Bridge Caissons (3b3023d3-bc2c-4a9b-8e78-d499291fb07f)By R. Bruce Patterson
The New Tacoma Narrows Bridge is a classic suspension bridge founded on concrete caissons. Caisson construction was complicated by the proximity of the existing bridge piers, only sixty feet away. H
Jan 1, 2004
-
Non-Destructive Geophysical Evaluation Of Deep-Mixed Soil: A Computer Modeling StudyBy David A. Staab
Numerical modeling was used to investigate the feasibility of using two geophysical imaging techniques, cross-borehole ground penetrating radar (XBGPR) tomography and electrical resistivity (ER) tomog
Jan 1, 2004
-
Advantages And Limitation Of Integrity Tests For Large Diameter Bored Piles In Bangkok SubsoilBy Narong Thasnanipan
In Bangkok due to the prevailing condition of subsoil (existence of considerably weak stratum at top part) deep-seated large diameter bored piles of over 50 m depth with 0.8 -1.8m in diameter have bee
Jan 1, 2004
-
Guide to Drafting a Specification for High Capacity Drilled and Grouted Micropiles for Structural SupportBy Donald Bruce
The three types of specifications which are used for micropile work are: ? Performance Specifications: The contractor is permitted control over certain design and/or construction procedures but must
Jan 1, 2004
-
The Construction And Performance Of Post-Grouted Micro-Piles For Vancouver International Airport Domestic Terminal Building - IntroductionBy Ernest Naesgaard
Post-grouted micro-piles were used for the seismic upgrading of the Vancouver International Airport Domestic Terminal Building (DTB). The micro-piles provided vertical resistance to both uplift and c
Jan 1, 2004
-
PSC Piles Overcome Challenges for $650m Power PlantBy Tim Siegel, III Fondren, Billy Camp
"INTRODUCTIONThe new $650 million power block at Santee Cooper’s Cross Generating Station in Cross, South Carolina is being constructed on driven pre-stressed concrete (PSC) piles. S&ME, as geotechnic
Jan 1, 2004