Innovative Use Of Piles For Retaining Sides Of Deep Excavations ? SynopsisBy D. V. Karandikar
Contiguous bored piles have been used in the past for retaining the sides of deep excavation. An innovative version of this method was adopted successfully in two prestigeous projects in Bombay in whi
Jan 1, 1996
-
100-Day Document - Mandatory Discussion, Mediation And Arbitration Of Construction Disputes ? 1.0 Coverage1.1 The parties agree to submit all claims, disputes or controversies arising out of, or in relation to, the interpretation, application or enforcement of this agreement, including dispute resolution
Jan 1, 1994
-
Prediction And Performance Of Drilled Shafts Constructed Under SlurryBy Clyde N. Baker
The paper describes procedures used to predict the settlement performance of drilled shafts constructed under slurry through water bearing deposits to a dense bearing strata, considering both side res
Jan 1, 1991
-
Report On An Instrumented Continuous Flight Auger Test Pile At Ascot.By Peter O. Wilkinson
Ascot Racecourse in the UK is a major international venue for horseracing. The racecourse is being redeveloped to provide entirely new public facilities. The development includes the construction of a
Jan 1, 2006
-
Rapid Vibratory Pile Driving Hammer For Deep FoundationBy Li Tiemin
It is one of important tasks in research of vibratory pile driving to increase speed of pile driving and depth of pile driving -- this means to increase capability of penetrating hard layer. In genera
Jan 1, 1991
-
Modulus of Elasticity in Deep Bored PilesBy Carlos Lam, Joram M. Amir, Erez I. Amir
"Abstract The modulus of elasticity of pile material (E) is an important parameter for the interpretation of both static and dynamic loading tests on piles. This value is commonly assumed to be consta
Jan 1, 2014
-
Resistance Factors For Lateral Design Of Drilled Shafts Supporting Sound WallsBy Ke Yang
Drilled shafts are widely used as foundation system for sound walls to resist lateral loads. The design method based on the ultimate lateral capacity, such as Broms method, is often used for sound wal
Jan 1, 2007
-
Hyperbolic P-Y Model For Static And Cyclic Lateral Loading Derived From Full-Scale Lateral Load Testing In Cemented Loess SoilsBy Steven Dapp
A new hyperbolic model for generating P-Y curves is developed for use in lateral analyses of cemented soils (a ?C-F? soil with both cohesive intercept and friction angle), and includes degradation of
Jan 1, 2011
-
A New Diaphragm Wall Technology Providing Mechanical And Watertightenss ContinuityBy P. Dupeuble
Diaphragm walls, owing to their method of construction are discontinuous structures. A new technology for the construction of joints between panels has been developed. This new process allows for the
Jan 1, 2010
-
Analysis Of A Deep Excavation In Calgary, AlbertaBy Thomas Lardner
Excavation for The Bow, EnCana, in downtown Calgary, occurred between May 2007 and September 2008. A monitoring programme was used to determine the behaviour of the shoring wall, soil and bedrock dur
Jan 1, 2010
-
Pile Design According to Eurocode 7, Highlights and DevelopmentsBy Adriaan van Seters
"Abstract The content of Eurocode 7 – Part 1 and Part 2 – with respect to piled foundations is outlined. The important role of pile testing is presented and the derivation of the characteristic value
Jan 1, 2014
-
In-Situ Permeability Testing For Cement-Bentonite Cutoff Wall ? Lessons LearnedBy François G. Bernardeau
Cement-bentonite (C-B) slurry walls have been used for ground water cutoff in deep excavations, contamination containment, and other applications. Hydraulic conductivity is of great concern for cement
Jan 1, 2008
-
Innovative Cofferdams Used On The I-205 Columbia River BridgeBy Robert Bittner
The following is a report on the development of two unique and separate cofferdam systems used in the construction of the marine foundations for the I-205 Columbia River Bridge at Portland, Oregon for
Jan 1, 2013
-
Measuring The Soil-Structure Interaction Of Laterally Loaded PilesBy Muhannad T. Suleiman
The design of deep foundations supporting heavy buildings, bridges, transmission lines, and highway structures, is governed by lateral loads in many cases. However, due to the use of empirical or semi
Jan 1, 2011
-
Large Diameter CIDH Construction In Cohesionless Soils By The Use Of Rotator/Ocsillator Techniques: A Case Study - 116th Avenue Bridge Over The Gila River Phoenix, Az.By M. Cornelius
Drilled shaft construction through caving soils has historically been an uncertain, risky and costly operation. Uncertain, because the zone of caving may or may not be known, risky because the loss of
Jan 1, 1999
-
Bearing Capacity Of Nodular PilesBy S. Kanai
Nodular piles is to be piles provided with several nodular projections along the pile shaft, as shown in Fig. 1. Nodular piles are usually installed through either driving method with hammer or prebor
Jan 1, 1989
-
Secant CFA- Pile Walls - A Risk Management ViewBy Mandy Korff
Walls consisting of CFA-piles are often used for vertical cut offs for building pits. Several methods of installation and geometry may be used and sizes, depths and strengths of walls necessary vary w
Jan 1, 2006
-
A Comparison Of Static And Statnamic Load Tests In Sand: A Case Study Of The Bayou Chico Bridge In Pensacola, Florida ? SummaryBy Michael D. Justason
This paper details the static and Statnamic load testing on a 600 mm square pre-stressed concrete pile. The pile was located at Pier 15 on the 20 million-dollar Bayou Chico Bridge Project in Pensacola
Jan 1, 1997
-
Deep Foundations In Hong Kong - SynopsisBy Martin Pratt
This paper is an overview of deep foundation engineering in Hong Kong past, present and future. The enormity of the subject compared with the space available makes brevity inevitable. Issues of constr
Jan 1, 2000
-
CPT - Guided Installation Of Pressure-Grouted Displacement PilesBy Mark M. Petersen
As part of the addition of eight new combined cycle generating units at the Florida Power & Light Sanford Plant, 2,129 piles were to be installed. The existing plant elements were supported on driven
Jan 1, 2002