  • AUSIMM
    Uranium Exploration in Australia

    Uranium minerals were found in Australia as early as 1869, but it was not until the 1940's that a search specifically for uranium was begun. Instrument types and techniques used in early explora

    Jan 1, 1970

  • AUSIMM
    Towards the Implementation of Discrete Fracture Network Modelling as a Geotechnical Design Tool – Case Study of Callie Underground Mine

    By S F. Rogers, K Doumis, J H. Graaf, B J. Barsanti

    Advances in technology now allow geotechnical practitioners to better describe the properties and variability of a rock mass through advances in surface and underground mapping, borehole technology an

    Nov 5, 2014

  • AUSIMM
    Optimisation of Complex Gold Processing Plants with Multiple Unit Operation Constraints – the Newcrest Planning Scheduler

    By D R. Seaman, R P. Tooher, B A. Seaman

    "Several mine scheduling tools exist for use in optimising and scheduling the reserve according to in situ value. These tools generally value the ore on a per block basis according to regressed recove

    Oct 10, 2016

  • AUSIMM
    Geometallurgy and Ore Processing of the Hibbing Taconite Lake Superior-Type Magnetite Taconite Deposit, Mesabi Iron Range, Minnesota, USA

    By J D. Lubben

    Hibbing Taconite is a Lake Superior-type granular magnetite taconite deposit occurring within the Biwabik Iron Formation along Minnesota’s central Mesabi Iron Range. The deposit is situated on the nor

    Jul 11, 2011

  • AUSIMM
    MMG Century Mine, A Case Study – Maximising Project Net Present Value Through Targeted Capital Expenditure and Process Optimisation Against a Backdrop of Falling Metal Prices and Feed Grades

    By R Wynn, T J. Akroyd, C Costa

    In an environment of lower zinc prices, falling revenues and reducing zinc feed grades, Century mine implemented a fast-tracked capital upgrade program in less than 15 months. The program was designed

    Sep 1, 2014

  • AUSIMM
    Bureau of Mines Diesel Research Highlights

    The goal of the Bureau of Mines, U. S. De- partment of the Interior, diesel engine research program is to reduce exhaust emissions and mini- mize the risk of fires and explosions caused by the use o

    Jan 1, 1988

  • AUSIMM
    NorandaÆs Approach to Evaluating a Competent Deposit for Caving

    By A Coulson, J Hussey

    Noranda Inc is a Canadian mining and metallurgical company with its activities managed through businesses in copper and recycling, zinc, aluminum, magnesium and various metals through its interest in

    Jan 1, 2000

  • AUSIMM
    The use of the Main Ramp as a Mine Exhaust at the Kencana Mine, Indonesia

    By D J. Brake

    Faced with the need to improve workplace conditions in both its development and production headings in its existing K1 orebody, as well as its new K Link and K2 orebodies, the Kencana mine in Indonesi

    Mar 21, 2011

  • AUSIMM
    Production Variance Benchmarks and Their Use in Project Evaluation and Due Diligence

    "Cash flow modelling during project evaluation is enhanced when probabilistic methods are applied to the inputs. One of the important inputs is the quarterly production profile. Typically, the steady-

    Mar 8, 2016

  • AUSIMM
    Case Study on the Remediation of a Remote Acid Mine Drainage Site in South Africa With Emphasis on Low Cost Measures and Cost Benefit Assessments

    By N Swiegelaar

    Loubert Witbank is a defunct coal mine situated near Ermelo in South Africa. Mining ceased in 1992, and within a short period acidic decant occurred, with a significant impact on the regional catchmen

    Jan 1, 2003

  • AUSIMM
    Operational Management of Underground In-Seam Drilling Sites

    By ZáWang, F Hungerford, T Ren

    Operations in an underground drill site have to co-exist within the mineÆs ventilation and operational system. The space requirements of a drilling operation have to be adapted to the limitations prov

    Jul 1, 2013

  • AUSIMM
    Mining Bench Height Evaluation for the Wallaby Resource ù A Conditional Simulation Case Study

    By M Titley, M NoppT

    A study on the feasibility of mining the recently discovered Wallaby gold deposit is due for completion by mid-2000. Open pit mining is the favoured method. Determination of the impact of mining bench

    Jan 1, 2000

  • AUSIMM
    Improvement of the copper flash smelting furnace (FSF) and the slag cleaning furnace (SCF) process by advice-based control of silica and coke addition

    By A Specht, A Müller, V Montenegro, S Winkler, E Klaffenbach, A Schmidt

    In the process of primary copper smelting in flash smelting furnace (FSF), the ratio of iron to silica (Fe/SiO2 mass ratio) primarily determines the slag viscosity and magnetite formation. Viscous sla

    Aug 21, 2024

  • AUSIMM
    Latest Experience with Dust Suppression in Tunnelling

    By Girnau G

    The necessity of effective dust suppression measures during excavation work is just as uncontroversial in tunnelling as it is in mining. In many respects, in fact, the applied technology is compara

    Jan 1, 1987

  • AUSIMM
    An approach to the calibration and validation of transfer chute DEM simulations handling cohesive iron ore fines

    By T Walkemeyer, R Elliott, D Chang-Martin

    Over the past decade, discrete element method (DEM) simulations have seen increasing adoption by the resources sector to inform the design of materials handling equipment such as transfer chutes, bins

    Sep 18, 2023

  • AUSIMM
    Ventilation Duct Leakage ù A Method of Assessment

    The tangible effects of leakage are presented graphically, and a technique for quantifying the leakage characteristics of a ventilation column using the æSolveÆ capabilities of a common spreadsheet is

    Jan 1, 2002

  • AUSIMM
    Carrapateena Vent Rise Performance – Geotechnical Design and Calibration

    By G Balog, T Ormerod, D Sidea

    Carrapateena is a copper-gold sub level caving operation located in the Gawler Craton, South Australia. One of Australia’s largest undeveloped copper deposits, the project will be a 4.25 Mtpa undergro

    Mar 15, 2021

  • AUSIMM
    30 years of seismic system design, implementation and interpretation

    By J Player, G Sweby, S Webber, E Jones

    Seismic systems are a tool for the monitoring and forecasting the rock mass response to excavation. Common issues encountered at mine site audits and reviews are: how to design an effective seismic sy

    Nov 29, 2022

  • AUSIMM
    The Impact of Fluidised-bed Flotation for Treating Coarse Sulfides

    By H Thanasekaran, M J. Mankosa, J N. Kohmuench, G H. Luttrell

    "Fluidised-bed flotation has been demonstrated over the last 16 years as an effective method for improving the flotation recovery of coarse particles. This technology has been successfully deployed in

    Oct 10, 2016

  • AUSIMM
    Recent Developments in Electrical Exploration

    The MIMDAS geophysical data acquisition system developed and tested by the former MIM Exploration Pty Ltd (MIMEX) is now commercially available worldwide through Geophysical Resources and Services Pty