    Session 15 "Jet Grouting IV"

    By Mitsuhiro Shibazki

    I can't answer that question but I am looking at Andy, my co-author, and he says we didn't measure it. No movement. If I understand it correctly, how do we handle lateral forces in shear? T

    Feb 10, 2003

  • DFI
    Design, Construction and Design Validation through High Strength Testing (PDA) of CFA and DD Foundations

    By Stefano Pirrello

    "Sydney’s booming real estate market has pushed property developers to invest in historically “no-go” areas, which were previously too expensive to develop. These areas are usually near rivers where t

    Jan 1, 1900

  • DFI
    Micropiled Foundations of Telecommunication Towers

    By Racquel Nottingham, Marc Mastrantuono, Freddy Lopez

    In the digital era that we live in, connectivity and mobility play a decisive role in our daily activities. In this context, insufficient telecommunication infrastructure gives origin to the so called

    Sep 8, 2021

  • DFI
    Monitoring Auger Cast in Place Pile Construction and Testing in Hard Clay (c1a730a8-7e87-4cd7-85b2-336e4f7995da)

    By Onur Guvener, Kalaiarasi Vembu, C. Vipulanandan

    "Installation procedure and the quality of the material used in the construction have significant effects on the behavior of the Auger Cast in Place (ACIP) piles. In this study, Installation and curin

    Jan 1, 2017

  • DFI
    A Geotechnical Data Base Development And Applying Data Mining Techniques To Extract The Common Trendes Of Offshore Geotechnical Properties Of South Pars Gas Field/ Persian Gulf IR-Iran

    By H. Shiri

    Iran's largest natural gas field is South Pars, geologically an extension of Qatar's 900-Tcf North Field. South Pars was first identified in 1988 and originally appraised at 128 Tcf in the e

    Jan 1, 2006

  • DFI
    Installation Of Augered Cast-In-Place Piles

    By Michael Moran

    Typical ACIP Pile Rig [ ] Hollow Stem Auger ? Continuous flight auger ? 3 inch inside diameter pipe ? Auger diameters: 12, 14, 16, 18, 20, 22, 24, 30, and 36 inches ? Auger section lengths:

    Jan 1, 2005

  • DFI
    Change In Bearing Capacity Of Bored Steel H Piles Enclosed In Soil-Cement Columns With Overburden Pressure - Synopsis

    By Tomio Tsuchiya

    A construction method of bored steel H piles enclosed in soil-cement columns was developed by modifying steel H piles from the driven pile method and soil-cement walls from the earth retaining wall me

    Jan 1, 1996

  • DFI
    Session 22 "Compaction Grouting and Limited Mobility Grouting"

    By Allen Cadden

    The type of soil we had was a silty fine sand. It had been placed by hydraulic methods in 1904 so it was quite clean I would say less than 10% silt the rest of it was very loose sand. That I'm n

    Feb 10, 2003

  • DFI
    Measurements of CDSM Strengths and Seepage Data Following Seismic Upgrades of San Pablo Dam

    By Atta B. Yiadom, A. David Miller, Robert C. Kirby, Sean M. Todaro

    "San Pablo Dam is a 170-foot (52-meter)-high earthfill embankment, located approximately 10 miles (16 kilometers) north of downtown Oakland, California, that impounds a 38,600 acre-feet (47.6 million

    Jan 1, 2015

  • DFI
    Alameda Corridor-East: San Gabriel Trench Project

    By David Peterson, Terry Tucker, Rafael Serrano

    "The Alameda Corridor-East (ACE) Construction Authority awarded a $172.6 million contract to Walsh Construction Company (Walsh) for the construction of a 2.2 mi (3.5 km) long grade separation includin

    Jan 1, 2017

  • DFI
    Designed, Load-Tested, And Installed Piles For A High-Rise Building In Southwest Florida - A Case History - Synopsis

    By Anupam Saxena

    This paper presents a case history of design, prediction, probe and production pile driving monitoring, loading test, and installation of piles for a 22-story condominium tower in southwest Florida, U

    Jan 1, 1996

  • DFI
    Axial Behavior of Auger Cast Piles in Inner Coastal Plain Geology (0a0de455-b1b9-4e2a-a87b-f9c3f26892a7)

    By Brian E. Ladd

    "A load test program was performed on two auger cast piles constructed in the Inner Coastal Plain geology of North Carolina. Both test piles were installed through Coastal Plain deposits and into unde

    Jan 1, 2017

  • DFI
    Virginia Route 340 Bridges: Challenges in Karst Terrain

    By Chaz Weaver, James Sheahan, Michael Mo

    "The Virginia Department of Transportation (VDOT) undertook a program to replace four bridges along approximately 4 mi (6.4 km) of US 340 in Northwest Virginia. Two of these bridges, which span Compto

    Jan 1, 2017

  • DFI
    Comprehensive QA/QC Integrity Testing Using Thermal Integrity Profiler

    By Brad W. Taylor

    "During the past several months, I have introduced to civil and structural engineers an innovative solution for the integrity testing of concrete using the Thermal Integrity Profiler (TIP) Wire Cable

    Jan 1, 2017

  • DFI
    The Value Of Field Measurement In The Design And Construction Of Deep Foundations ? Synopsis

    By J. P. Burland

    The paper describes a number of recent case histories in the United Kingdom where field instrumentation and measurements have played a major role in the design and construction of excavations, piles a

    Jan 1, 2010

  • DFI
    Session 31 "Grout Mixtures and Materials 2"

    By Lois G. Schwarz

    I did not make studies about this parameter but I can say that some researchers recommend using low C3A cements to repair masonry mortar in order to reduce a possible combination with sulphate that ca

    Feb 10, 2003

  • DFI
    The Impact Of End Bearing Plate On Micropile Capacity Casted In Cohesive Soil

    By Soorkty Elarabi

    The aim of this paper is to discuss the impact of end bearing plate on the capacity of micropile. Preliminary studies have been made in Sudan in specific area of cohesive soil. Experimental works were

    Oct 1, 2022

  • DFI
    Case Study of Deep Mix Pile Supported Diaphragm Wall for a Stilling Basin Structure in Malaysia

    By Chandrasegaran, Tamilmani

    "This paper describes a case study of a retaining wall structure using a diaphragm wall to construct a stilling basin at Tanjung Bin T4 power plant in Johor Bahru, Malaysia. The stilling basin is part

    Jan 1, 2015

  • DFI
    Design And Construction Of The Large Bored Piles For A Bridge Over The Yellow River ? Synopsis

    By Y. Z. Wang

    Zhengzhou Yellow River Highway Bridge, which is under construction, has a total length of 5550 meters with bored cast-in-place concrete piles as the foundations of its piers which have a diameter of 2

    Jan 1, 2010

  • DFI
    Session 14 "Deep Mixing Method III"

    By Stefan Dahlin

    The laboratory tests indicated low permeability but as I said, as a rule, the permeability in the field has been found to be higher. A high permeability has also been found when doing back calculation

    Feb 10, 2003