    A Practical, Yet Technically Sound, Design Procedure for Pre-Split Blasts

    By William Hustrulid

    Pre-split blasting is a primary technique for creating slopes with a minimum amount of unwanted damage to the remaining rock mass. Rock slopes created in such a way have both safety-related and econom

    Jan 1, 2007

  • SME
    Can community-based mining support rural sustainable development objectives in Nigeria?

    By I. T. Oramah

    Despite the abundance of solid mineral deposits, Nigeria only earns about 0.5-1% of its current Gross Domestic Product (GDP) from the solid minerals sector. This is as a result of the dominance of the

    Jan 1, 2011

  • CIM
    Mine Planning Guidelines for Developing Sustainable Closure Drainage Systems

    By Leslie F. Sawatsky

    Failure of drainage works is one of the principal threats to the sustainability of mine closure facilities but the risk can largely be remedied by appropriate design of mine closure drainage facilitie

    May 1, 2004

  • NIOSH
    The Effects Of Restricted Workspace On Lumbar Spine Loading

    By Mark S. Redfern, Kim M. Corneliusa, Christopher A. Hamrick, Sean Gallaghera

    Coal miners often handle heavy electrical power cables, weighing up to 10 kg per meter. These cables are manually lifted and attached to the mine roof to prevent damage from mobile underground equipme

  • AIME
    Development Of The Choking-Free Cyclone And Its Classification Performance

    By T. Sekimoto, T. Kokubo, M. Yamamoto, K. Masuda, T. Moro, H. Sakamoto

    The choking-free cyclone was developed primarily to remove solid particles suspended in a slurry containing fibrous materials, such as municipal solid waste. This cyclone is characterized by a screw c

    Jan 1, 1980

  • SME
    Geotechnical Conditions and TBM Selection for the Bay Tunnel

    By Luke Erickson

    San Francisco Public Utilities Commission is planning to replace 5 miles of pipeline under San Francisco Bay. The tunnel will be constructed using an Earth Pressure Balance (EPB) TBM and will be the f

    Jan 1, 2008

  • SME
    Stability Analysis For Steep-Slope Mines Reclaimed Using The Forestry Reclamantion Approach

    The Forestry Reclamation Approach (FRA) specifies that the upper 1.22 m of material on the reclaimed surface should be left as uncompacted as possible to facilitate tree root growth. One of the main c

    Feb 27, 2013

  • CIM
    Metallurgical Testing of Gold Ores

    By T. Salman

    Most authorities agree that the dissolution of gold from an ore takes place according to the Elsner equation first stated in 1846. The main requirements for the dissolution reaction to proceed are:(1)

    Jan 1, 1975

  • SME
    A Dissolution Kinetic Model For Metal Powders A Case Of Varying Surface Area

    By Kenneth N. Han, Peter Nam-soo Kim

    A kinetic model for leaching of particulate metals in a batch system has been developed. The leaching mechanism has been analyzed by solving a series of ordinary differential equations relating hetero

    Jan 1, 2005

  • IMPC
    Improving Mine and Metallurgical Performance Using: Data Unification and Measurement Management

    By Osvaldo A. Bascur, J. Pat Kennedy

    "The profitability of mining and metallurgical operations continues to lag behind that of other industries despite the technical advances that have occurred in recent years. A primary reason for poor

    Jan 1, 2003

  • AIME
    Reservoir Engineering – General - A Method for Determining Optimum Second Stage Pressure in Three Stage Separation

    By Kenneth F. Whinery, John M. Campbell

    Basically, the Buckley-Leverett theory involves two systems which are similar in nature but are differentiated by time. These systems may be described by the fractional flow and frontal advance equati

  • SME
    Improving Empire?s Grinding Circuit Performance Using Six Sigma - Preprint 09-059

    By H. Walqui

    The Empire concentrator was built in four stages, with the latest stage accounting for 50% of the overall plant capacity. Over the past 5 years, the average throughput of the three grinding lines has

    Jan 1, 2009

  • AUSIMM
    Cultural Challenges in Chinese/Australian Mining Mergers and Acquisitions - A CEOÆs Perspective

    By Y Zhu, W Liang, P Knights

    In recent years, Chinese companies have invested billions in Australian mineral exploration, development and processing. In 2008 - 2009 alone, the Foreign Investment Review Board approved $26.4 B of i

    Nov 20, 2012

  • ISEE
    Investigation of Ground Vibration at Gulyali Basalt Mine in Turkey

    By Ali Kahriman, Alper Celtikc, Serdar Celik, Tuncer Gungor

    This paper presents the results of ground vibration measurements carried out in Gülyali Hisarcik Basalt open pit mine located on the north side of the Anatolia near Ordu province in Turkey. Within the

    Jan 1, 2013

  • SME
    Responsible coal sourcing - taking the next step

    By R. Strandahl

    As one of the largest private utilities globally, E.ON currently operates hard coal fired power stations in with a total installed capacity of some 20.000 MW: These thermal power plants consume domest

    Jan 1, 2011

  • CIM
    A Protocol for Conducting Plant Trials Testing Grinding Media to Determine Recovery Improvements: The Ernest Henry Mine Plant Trial

    By Allen Chung, John Twomey, Christopher J. Greet

    "It is widely accepted that the type of grinding media has an impact on the grinding chemistry and subsequent flotation behaviour of the sulphide minerals being separated. There are countless laborato

    Jan 1, 2011

  • NIOSH
    Employment And Injuries In The Metal And Nonmetal Industries (f0df1e9c-d44c-4f72-91b8-6b254e76201f)

    By Forrest T. Moyer

    INJURY experience in the metal and nonmetal mineral industries during 1964 was better in rates of occurrence but worse in severity rates than in 1963. The frequency rate of injuries per million man-ho

    Jan 1, 1965

  • SME
    Risk Considerations and Design for the Downtown Deep Sewer Tunnels, Austin, Texas

    By Greg Wieland

    Deep sewer tunnels are required to meet future growth demands of the City of Austin?s down-town redevelopment. The tunnel is 18,000 ft long and varies in finished diameter from 54 inches to 96 inches.

    Jan 1, 2008

  • NIOSH
    RI 4444 National Motor-Gasoline Survey, Summer 1948

    By O. C. Blade

    This report on the properties of motor fuels sold through service stations in the United states was made in accordance with a cooperative agreement between the American Petroleum Institute and the Bur

    Jan 1, 1948

  • IMPC
    Production of Phosphate Concentrates from Slimes: Brazilian Experience

    By Rogerio C. Guimarães, Antonio E. C. Peres

    The production of phosphate concentrates (phosphate rock) from slimes represents a challenge to the phosphate industry worldwide. In Brazil, this challenge is particularly relevant due to the consiste