    Reliability Analysis Of Load Bearing Capacity Of Single Pile Placed Adjacent To Existing Buried Conduit Or Utility Tunnel

    By Amit Srivastava, Monica Malhotra

    In a congested city or urban area, so called “lifeline of the city”, i.e. Gas, Electricity, telecommunication, as well as other utilities or facilities are supplied or transported underground through

    Sep 1, 2022

  • DFI
    Elimination of Environmental Footprint: LVCC Expansion - Foundation Installation

    By Zachary Q. Maassen

    Upon approval from the Las Vegas Convention and Visitors Authority (LVCVA), Turner/Martin Harris, A Joint Venture began construction on the estimated $860 million expansion for the Las Vegas Conventio

    Jan 1, 2019

  • DFI
    Low Overhead Secant Piles Drilled From Within A Shaft

    By Allen B. Stanton, Parthiv Brahmbhatt, Michael Grimm, Stanley L. Worst

    Constructing a circular shaft consisting of secant piles has its own complications which make it more difficult than typical drilled shaft construction. Add to that performing under low overhead power

    Oct 1, 2022

  • DFI
    Concrete Piles Driven In A Coral Sand

    By L. D. Johnson

    12 groups of 12 precast prestressed (PCPS) piles were driven in the lagoon of Kwajalein Island to support a dry dock. Pre-construction investigation of the calcareous coral sands and static pile loeid

    Jan 1, 1993

  • DFI
    Lateral Pressure Relief by Geotextile Encased Columns (GECs) at Piled Bridge Abutments: Two Case Studies

    By Sven Schröer, Lilma Schimmel, Dimiter Alexiew

    "The Geotextile Encased Columns (GEC) deep foundation system for embankments on soft soils was introduced some 20 years ago and is now considered State-of-the-art worldwide.The GECs consist of compact

    Jan 1, 2016

  • DFI
    Jobsite Safety Inspection Checklist

    By Sam Messina

    [Project: Job Number: Date: Superintendent: Person Making Inspection: Note: The following checklist shall be used on a regular basis as an overall assessment of the jobsite. The checklist

    Jan 1, 1998

  • DFI
    Behavior of a Piled Raft in Dry Cohesionless Soil Subjected to Lateral Loading

    By Srijit Bandyopadhyay, Aniruddha Sengupta, G. R. Reddy, Raj Banerjee

    The objective of the present endeavor is to compare the performance of a pile raft system in foundation sand subjected to lateral loads. To study the behavior of pile raft system in sand a laboratory

    Jan 1, 2015

  • DFI
    Comparison Of Large Plate Load Test Result With Predicted Deformation In Deep Vibro Techniques Treated Ground For Iron Ore Stockpile Yard In Vietnam

    By Leong, William. Chong, Kam Weng

    Deep Vibro Techniques namely Vibro Compaction (VC) and Vibro Replacement (VR) are widely used in ground improvement to densify sands and strengthen cohesive soils. This paper describes the application

    Nov 1, 2022

  • DFI
    Numerical Study On Uplift Capacity Of Helical Pile Embedded In Clay

    By Muttharam M, Karthick Kumar V

    Helical piles foundation systems have been extensively used in engineering application. It is commonly adopted to resist the compression, uplift force, overturning moment and lateral forces. Helical p

    Nov 1, 2022

  • DFI
    Response of Pile and Pile Groups against Excavation Induced Ground Movement

    By K Ilamparuthi, R. K. Madhumathi

    "This paper presents the results of 1g model tests conducted on model piles both single and two pile groups embedded in sand by physically inducing lateral soil movement. From the test results it was

    Jan 1, 2015

  • DFI
    Experimental Studies On Behaviour Of Single Pile Under Combined Uplift And Lateral Loads

    By K. Madhusudan Reddy

    Pile response under combined uplift and lateral load is very important and it is imperative to evaluate the effect of combined loading and only few studies were reported on pile behavior under combine

  • DFI
    Gordie Howe International Bridge Foundations - Drilled Shaft Construction in Challenging Detroit Limestone

    By Jim Glider, Noah Miner

    The Gordie Howe International Bridge is a project to build a cable-stayed bridge and border crossing across the Detroit River. With a span length of 2,800-ft (853.4 meters), the Gordie Howe Internatio

    Sep 8, 2021

  • DFI
    “Borehole Stabilization” For Deep Excavation, An Essential Part In Bored Piling / Diaphragm Wall Construction

    By Thomas Domanski

    Any type of deep excavation whether for Bored Piling, Diaphragm Walls or Contiguous Bored Piling Walls depends on forming a stable borehole with a defined cross-section to receive safely the permanent

    Sep 1, 2022

  • DFI
    Design And Performance Evaluation Of A Grouting Program In Weak Rock Masses

    By George Moses K, Mahendran K

    Grouting is performed in rock masses in order to increase its strength properties and also to reduce the seepage. In the design of underground structures such as tunnels or caverns located in weak roc

    Nov 1, 2022

  • DFI
    Cost Effective Excavation Support in Seattle

    By Richard D. Luark, Fernanda S. Madrona

    Deep foundation construction in highly developed urban settings pose unique challenges of working with deep excavations in a relatively confined area while preserving the integrity of nearby structure

    Jan 1, 2019

  • DFI
    Design Of Bored Piles In Chalk At The New Medway Crossing Based On Instrumented Load Tests

    By David J. Puller

    As part of the value engineering process on a major Design Build highway project, instrumented trial pile load tests were used to achieve savings in cost and time on the foundations for a major river

    Jan 1, 2002

  • DFI
    Drawdown of Ground Water Control System in Deep Excavation Surrounded by Cutoff Walls: Numerical Investigation

    By Dalia. R. Mohamed, Hisham H. Hafez, Marawan M. Shahien

    "Construction activities in major projects that involve deep excavations necessitate the use of vertical walls surrounding the construction site to play an important role as earth retention system. Th

    Jan 1, 2016

  • DFI
    Instrumented Hybrid Shoring System for a Deep Temporary Excavation Incorporating Cutter Soil Mixing in Vancouver, BC, Canada

    By Nadir Ansari, Brian W. Wilson, Marina S. W. Li

    "A hybrid shoring system consisting of cast-in-place soldier piles with Cutter Soil Mixing (CSM) infill panels was constructed for temporary support of a 19.8 m (65 ft) deep excavation in Vancouver, B

    Jan 1, 2017

  • DFI
    Helical Pile-to-Pile Cap Connections Subjected To Uplift Forces: Improving Future Practice

    By Serhan Guner, Sundar Chiluwal

    Although significant research has been conducted on helical piles, there is a lack of research and official design provisions on the helical pile-to-pile cap connections. These connections may govern

    Jan 1, 2019

  • DFI
    East Boston Branch Sewer Relief Project: Support Of Excavation Case Study

    By Eric P. Bregman

    As part of an on-going effort to improve water quality and reduce discharge into Boston Harbor, the Massachusetts Water Resources Authority (MWRA) East Boston Branch Sewer Relief Project was designed