    Design Of The BMIP Boat Section - Introduction

    By Kenneth Pidgeon

    The Boston Marine Industrial Park (BMIP) Boat Section, which is part of contract C04A2 of the Central Artery/Tunnel (CA/T) project, is currently under construction in South Boston, Massachusetts (Fig.

    Jan 1, 1994

  • DFI
    Construction Of Foundation Of Power House-IV At W.Y.C., Hydro-Electric Project, H.S.E.B., Bhudkalan, Haryana. - Synopsis

    By D. K. ] [Gupta

    The Foundations of the Shear keys and alround cut off for Power House -IV of the Western Yamuna Canal Hydroelectric Project at Bhudkalan, Haryana were to be laid at a depth of 26M below the N.S.L and

    Jan 1, 1996

  • DFI
    Underpinning Historic Museum for U-505 Submarine Relocation

    By Goudschaal Mark R.

    "The Museum of Science and Industry U-505 Submarine Relocation project in Chicago, IL consisted of building an underground reinforced concrete vault (37' deep) for the Museum's new U-505 exhibit. This

    Jan 1, 2005

  • DFI
    Load In A Drilled Foundation. Where Did It Go And When Did It Get There?

    By Walter E. Vanderpool

    Three drilled foundations for an elevated water-tank were instrumented, tested and monitored during construction and the first two years in service. One shaft was load tested by the Osterberg method.

    Jan 1, 2004

  • DFI
    Behavior Of Excavation And Pile Foundations In Soft Bankok Clay

    By D. T. Bergado

    The uppermost subsoil profiles of the Bangkok plain can be divided into four layers, namely: weathered clay, soft clay, stiff clay, and dense sand layers. The soft Bangkok clay is a normally consolida

    Jan 1, 2010

  • DFI
    Ground Freezing Combined Method for Urban Tunnel Excavation

    By Filippo Mira-Cattò, Andrea M. R. Pettinaroli, Elena Rovetto

    "The construction of Powisle station of Metro Warsaw Line 2, in Poland, required the execution of two shafts next to an urban road tunnel adjacent to the Vistula River. The shafts were linked by three

    Jan 1, 2015

  • DFI
    State-Of-Art Working Platform For Heavy Equipments Used For Deep Foundation Construction

    By Arunsiva R., Sivaranan S., Venugopal B., Kumaran M.

    Being a rapidly developing country, India is undergoing a massive infrastructure phase change remarkably. The construction industry is already set to boom, but the time and space constraints necessita

    Sep 1, 2022

  • DFI
    An Unique Formula for the Stone-Column Group Efficiency

    By Abhijit Saha

    "The stone columns improve the performance of foundations on soft and loose soil due to the ability of composite ground to sustain increased structural loads under reduced settlements. The interaction

    Jan 1, 2015

  • DFI
    Geotechnical Monitoring Of Deep Shoring Adjacent To Train Infrastructure

    By Jakub Szary

    Excavation and shoring adjacent to the above-grade Gilmore train station and elevated guideway was undertaken in 2019. A perimeter secant pile cut-off wall was constructed to a depth 37 m (121 ft) bel

    Sep 1, 2022

  • DFI
    Analysis of Panel and Pile Verticality and Overlap in a Project Information Management System

    By Jamey Rosen, Georgette Hlepas

    Verticality data collected from panel and pile elements of seepage barrier walls describe the shape and position of those elements in three dimensions. These data are used to determine if a barrier wa

    Sep 8, 2021

  • DFI
    Performance of Foundation Systems in Chicago

    By William (Bill) H. Walton

    "I arrived in Chicago in 1993 with Dr. Ralph Peck’s University of Illinois bulletin titled Engineering Properties of Chicago Subsoils (Bulletin 429), which he published in 1954 with William Reed. Bein

    Jan 1, 2017

  • DFI
    The Effect Of Vertical Pile Loading On Subsequent Lateral Behaviour

    By A. Lyndon

    Vertical and lateral load tests were carried out on two 13 m deep bored cast-in-place instrumented piles, socketed into weathered sandstone. The first pile, 1200 mm in diameter, was loaded vertically

    Jan 1, 1989

  • DFI
    LRFD and Its Implications for QC/QA of Deep Foundations

    By Bernard Hertlein, Chia K. Tan

    "The move to LRFD methods for structural design by AASHTO, ACI, AISC , ASCE, and the FHWA has been a major change for the American construction industry. The deep foundations industry has arguably bee

    Jan 1, 2005

  • DFI
  • DFI
    Risk Management Techniques to Avoid Litigation

    By Kevin Cunningham

    "Litigation resulting from neighboring structures with settlement and/or lateral movement or improper pile design and faulty soils engineering analysis, are a multi-faceted opportunity for law firms.

    Jan 1, 2015

  • DFI
    Non-Destructive Testing Of Drilled Shafts - Title ? Table Of Contents - Introduction And Overview

    By Edmund J. Cardoza

    WELCOME TO THE DEEP FOUNDATIONS INSTITUTE 26TH ANNUAL CONFERENCE AND WELCOME ESPECIALLY TO THIS SEMINAR ON NON-DESTRUCTIVE TESTING OF DRILLED SHAFTS, PRESENTED BY MEMBERS OF THE DFI DRILLED SHAFT COMM

    Jan 1, 2001

  • DFI
    Historical Evolution Of Deep Foundations

    By Dean E. Matthews

    The concept of a pile for construction is credited to a Neolithic tribe called the "Swiss Lake Dwellers" who lived in what is now Switzerland about 6,000 years ago. They used piling, not for supportin

    Jan 1, 2003

  • DFI
    Performance Of A Large Diameter Drilled Pier (f4c3f0c8-a45b-48d0-8d0a-138a34a08ce3)

    By A. J. Partos

    The figures and tables referred to herein are presented in the Proceedings; Volume I, Pages 309 through 316. The 61-story One Liberty Place, at 315 m., is the tallest building 1n Philadelphia and

    Jan 1, 1991

  • DFI
    The Evolution of Augered Cast-in-Place Piles

    By Willie M. NeSmith, W. Morgan NeSmith, Alan Roach

    "In 2013, Augered Cast-in-Place (ACIP) piles are a mature foundation technology throughout the United States. General guidelines for the design and construction of ACIP piles are available along with

    Jan 1, 2013

  • DFI
    Hybrid Shoring Solutions for a Challenging Excavation Project Adjacent to a Subway – 21 Avenue Road, Toronto

    By Graeme Smart, Thomas Fiala

    "Yorkville Plaza II, a 40-storey signature condominium residence, is scheduled to open on Avenue Road in Toronto’s prestigious Bloor-Yorkville neighbourhood in spring 2017. In close proximity to Toron