Aluminium ExtractionThe Hall-Heroult process is likely to be the dominant method of aluminium production for the remainder of the century. The characteristics of the operation of a modern smelter are described and attent
Jan 1, 1987
-
Some Environment Aspects of Aluminium ProductionAluminium in Australia, and in fact all round the world, is made virtually exclusively by the Hall-Heroult process, whereby the metal is derived from the electrolysis of alumina dissolved in an ele
Jan 1, 1977
-
Modelling of the Chemical Speciation of Cyanide Species û Application to Effluent TreatmentBy Tran T, Young D
During the processing of gold, effluents that are discharged into the tailing dams contain free cyanide, metal cyanide complexes of zinc, copper, iron, etc and their oxidised products such as ammoni
Jan 1, 1991
-
Use and Performance of Bucketwheel Excavators in the Latrobe Valley CoalfieldsBy Laird CH
Large quantities of brown coal are excava ted from open cut mines in the Latrobe Valley to fire the base load thermal power stations of the Victorian Electricity System. Most of the coal is removed
Jan 1, 1978
-
The Oscillating Disc Cutter - The Breakthrough Tool for Continuous Rock ExcavationBy X Li, H Alehossein
The oscillating disc cutter (ODC) is an innovative technology for the continuous excavation of hard rock. This paper will discuss:the reasons for its development;its method of operation;current experi
Jan 1, 1999
-
Remnant MiningAs world demand for various minerals increases the mining industry in its endeavour to satisfy this demand will, eventually,look to the extraction of orebodies which previously may have been uneco
Jan 1, 1975
-
Design Procedure and Results from a Field Test of Soil Freezing as Stabilisation of Bottom Slice FillBy P Andersson, P Marklund
Evaluation of different techniques for bottom fill stabilisation showed that frozen fill was the most economical method. In order to test the method a full-scale field test was performed in the Rehnst
Jan 1, 1998
-
Transport in Drifts and ShaftsFrom depths of 400 - 600 m, coal is transported by a conveyor in a drift or a bulk winder in a shaft, whilst men and/or materials are transported by a slope hauler or a cage winder. Assessment of t
Jan 1, 1976
-
Integrated Approach to Mine Groundwater AssessmentBy B Mil, D P. Adhikary, M S. Craig, P Rutzou
As shallow coal reserves with easier mining conditions are exhausted, future deep coal mining with difficult mining conditions may face significant economic, technical and environmental challenges. Mo
Jan 1, 2006
-
Improving Sampling Methodology for the Evaluation of Fines Production at Vanderbijl Park Sinter Plant, South AfricaBy J P. R de Villiers
The Vanderbijl Park sinter plant in South Africa was investigated to determine the reason for the production of very fine sinter not acceptable as feedstock for the blast furnace. A procedure was desi
Jan 1, 2008
-
An Alternative to Cube-root Scaling Crater AnalysisBy Fourney W. L, Weaver T. A
A large number of single borehole crater-forming shots were analyzed in terms of correlating the crater parameters with explosive weight. The objective was to determine a scaling rule for which the
Jan 1, 1990
-
Non-Contact Acoustic Measurement of Dynamic In-Mill Processes for SAG/AG MillsBy R A. Pax
Heavy machinery such as AG and SAG mills generate a significant amount of noise due to the processes that are occurring inside them. From an environmental perspective, the level of noise generated is
Aug 8, 2011
-
Management of Ranger Uranium Mine Waters, Kakadu Region, Northern Territory, AustraliaBy Bastias J
The Ranger uranium mine has operated in the Kakadu region of the Northern Territory since 1979. The mine's water management system was designed to cater for the wet-dry monsoonal climate and to
Jan 1, 1988
-
Determination of Groundwater Inflow Rates for Longwall Mining, German Creek, Bowen Basin, QueenslandBy Phillips RN
Semi-confined, trachy-andesite sills which overlie the German Creek Seam, within the critical tensile strain zone, form major groundwater hazards to longwall mining at the German Creek underground
Jan 1, 1988
-
Design, Construction and Commissioning of A 4 Tonne/Hour Matte Fuming Pilot PlantBy Lightfoot BW, Foo KA, Conochie DS
Aberfoyle Limited operated a matte fuming pilot plant, incorporating a SIROSMELT furnace in 1980/81. This plant was a significant advance in both smelting and tin extraction technology. Important
Jan 1, 1984
-
Traversing the Valley of Death – upscaling the REFLUX™ flotation cellBy M J. Cole, J Zhou, D J. Borrow, S M. Iveson, K P. Galvin, J L. Sutherland
New technologies can easily take around ten years to commercialise. Strong research support is needed in parallel with the process of innovation and commercialisation, in building a deeper understandi
Aug 24, 2022
-
Mechanised Development At The Kambalda DeclinesThis paper deals with the evolution of present mechanised declining and orebody development practices at Kambalda, since their inception in 1969. Eight separate decline accesses have been establis
Jan 1, 1987
-
Paraprofessional Education in the Metallurgical and Related IndustriesThe development of paraprofessional courses in metallurgy and related disciplines, by the Department of Technical and Further Education in New South Wales, is outlined in this paper. The changing n
Jan 1, 1978
-
Risk Assessment in a Long Term Mining Contract - The Contractor's ViewpointInternational tenders for contract mining opportunities require the Contractor to make an assessment of risk for an operation with a life span of up to twenty-five years usually based on data mad
Jan 1, 1986
-
Monolithic Partitions for the Wide Drivages - Some Design ConsiderationsThe paper examines the possibility of applying the monolithic packing technique developed in the UK to the division of wide development drivages in Australia, so enabling double entries for longwal
Jan 1, 1986