Southwest Interceptor Contract No. 1 - A Case HistoryBy Victor J. Scaravilli, C. Richard Linamen
This paper presents a case history of Southwest Interceptor Contract No. 1, Cleveland, Ohio. It details some of the problems and solutions of handling and erecting precast concrete segments in a small
Jan 1, 1987
-
Educating the Coal Mining Industry in the Field of Engineering Health and SafetyBy Albert W. Evans
Introduction Engineering Health and Safety is concerned with the understanding of the complex interplay between the risk of injury with technological ,environmental, individual, organisational and
Jan 1, 1986
-
Stability Problems Caused By Seams And FaultsBy T. L. Brekke, T. R. Howard
Stability of an underground opening can be defined in several ways. To geologists and engineers that are used to working in geological environments where the major parts of the works after careful sca
Jan 1, 1997
-
Mineral Policies and Land Use Planning in two Central European and two Nordic Countries with a Long Metal Mining HistoryBy K. Nielsen, V. Bauer
"The paper presents a brief overview of the long mining history and the more recent political development in the Slovak and Czech Republics as well as in Norway and Sweden. Mining used to be very impo
Jan 1, 2005
-
NATM Provides Improved Design And Construction Method For U.S. Tunnel ProjectsBy G. W. Rhodes, B. P. Cavan, F. K. Mussger
The New Austrian Tunneling Method (NATM) has been successfully applied to two very different tunneling projects in the U.S.. In the case of Pittsburgh's Mt. Lebanon Tunnels, two original design a
Jan 1, 1985
-
Copper Mineral Reactions In Supercritical And Subcritical WaterBy A. E. Isaacson
The Bureau of Mines is studying the effect of supercritical water, at 4000 C and 3,500 psi and subcritical water at lower temperatures and pressures. on mixtures of minerals and metals to determine th
Jan 1, 1989
-
Probe Drilling For Rapid TunnelingBy R. L. Schmidt, Williamson. T. N.
INTRODUCTION This paper describes one of several research projects funded by the Advanced Research Projects Agency to extend the technology of rapid underground excavation. This study and field res
Jan 1, 1997
-
Effect Of Application Frequency of Asphaltic Gear Spray Lubricant On PerformanceBy H. Benedict
For many years, asphaltic lubricants have been used on large open gears. The asphaltic's diluent is essential to thin the lubricant enough to be sprayed. Once the lubricant has been sprayed int
Jan 1, 2003
-
Phosphate Industry And Environmental ControlBy Bruce Congleton
The Florida phosphate industry is a leader in environmental control, both in terms of dollars spent and significant achievements. For instance, since 1960 the phosphate industry has spent over $71 mi
Jan 1, 1972
-
Ground Freezing For Soft Ground Shaft SinkingBy John A. Shuster
Case histories are reported for several soft ground shafts ranging from 6' to 40' in diameter and 50' to 230' in overburden depth for which ground freezing was employed to provide
Jan 1, 1985
-
Construction Of Large Diameter Shafts With Reinforced Concrete Ring BeansBy Daniel L. Hanson
This paper presents case histories of the construction of four large diameter circular shafts using reinforced concrete ring beams as the primary internal support system. The case histories pertain to
Jan 1, 1987
-
Effects Of Seasonal Temperature Changes On Autogenous Milling PerformanceBy S. K. Kawatra
Although temperature is known to have a substantial effect on many processes, this parameter has been widely dismissed as insignificant for mineral comminution. For this reason, temperature effects on
Jan 1, 1989
-
Transport Improvements Through Slurry TechnologySlurry technology developed for the marine transport of mineral commodities has been increasingly applied to on-shore slurry transport systems. Reclaim of mineral concentrates, sand tailings for mine
Jan 1, 1986
-
Some Considerations In The Design Of Blasts For In Situ Copper LeachingBy Dennis V. D’Andrea, Peter G. Chamberlain, James J. Olson, William C. Larson
Blasts designed for in situ copper leaching must produce adequate fragmentation and permeability for successful leaching. Copper recovery depends to a large extent on the particle size distribution cr
Jan 1, 1977
-
Eisenhower Memorial Tunnel - How Colorado Department Of Highways Improved Contracting Practices And ManagementBy P. R. McOllough
The Colorado Department of Highways awarded a contract to construct the Second Bore of the Eisenhower Tunnel in August, 1975. The contract was completed June 29, 1979, nine days ahead of schedule, wit
Jan 1, 1981
-
Communication In DiversityBy Robert L. Bates
The field of industrial minerals and rocks includes such a wide diversity of materials and occurrences that communication is essential to foster a sense of "belonging? among geologists and other profe
Jan 1, 1995
-
Research and Development in Developing Countries - Assistance of UNIDOBy E. T. Balazs
Share of developing countries in world bauxite resources mining and processing. Technical assistance of the United Nations Industrial Development Organization to the developing world in the field of b
Jan 1, 1984
-
Blasting Techniques And Safeguards Used In Enlarging The Underground Powerhouse At Salto De Villarino, SpainBy J. Y. Perez, H. M. Ewoldsen, L. L. Oriard
Near the village of Villarino de los Aires, in the province of Salamanca, Spain, is an existing underground hydroelectric power plant. A major enlargement was undertaken to increase the electrical gen
Jan 1, 1974
-
Fast Tunneling With Drill & Blast Tunnel and Shaft Construction at the Sixth Water AqueductBy Bruce McKinstry
INTRODUCTION In June of 1992, the Bureau of Reclamation, United States Department of the Interior, awarded the contract for construction of the Sixth Water Aqueduct to the Fedrick-Redpath Joint Ventu
Jan 1, 1995
-
Geotechnical Performance Of A Large Machine-Bored Precast Concrete Lined TunnelBy Edwin A. Blackey, Joseph G. Engels, James T. Cahill
An extensive geotechnical instrumentation program was undertaken during the construction of a 6.7 m (22 ft) inside diameter tunnel to monitor the ground-structure response and to check assumptions mad