  • NIOSH
    IC 6605 Milling Methods And Costs At The Pecos Concentrator Of The American Metal Co., Tererro, N. Mex. - Introduction

    By H. D. Bemis

    This paper describing the milling practice of the American Metal Co. at its Pecos con¬centrator is one of a series on milling methods and costs being prepared by the United States Bureau of Mines.

    Jan 1, 1932

  • SME
    Design Considerations For Mining Thick Seams And Seams Lying In Close Proximity To One Another

    By J. W. Wilson, S. Nakajima, B. D. Singh

    According to the Project Independence blueprint, a 270 percent increase in coal production is expected from western coal fields compared to an increase of 100 percent for the nation as a whole. Furthe

    Jan 1, 1977

  • SAIMM
    Numerical and Physical Modelling of Tundish Slag Entrainment in the Steelmaking Process

    By S. Bradshaw, A. Mabentsela

    "Physical and numerical modelling methods were followed to identify mechanism(s) for tundish slag entrainment in a bare tundish and one with a flow control device (FCD).The physical and numerical mode

    Jan 1, 2017

  • DFI
    High Capacity Barrettes In A Region Of Old Underground Quarries

    By F. Schlosser

    The extension of Montparnasse Station in Paris required the construction of supports of very high unit capacity to support a particularly rigid super-structure. The majority of the site is characteriz

    Jan 1, 1989

  • SME
    Geologist's Gordian Knot: To Cut Or Not To Cut

    By I. S. Parrish

    As noted by McKinstry (1948), "How to deal with erratic high samples is one of the knottiest problems in ore estimation." He described a variety of approaches and methods to alleviate the problem thro

    Jan 1, 1997

  • AUSIMM
    Radar guided blasthole drilling improves product recovery

    By I Mason, M van de Werken, B Zhou, J Hargreaves, W Stasinowsky

    A critical step in open cut coal mining is clean removal of the overburden. This is usually achieved by drilling, blasting and digging. A key part of this process being successful is to stop drilling

    Sep 1, 2024

  • AUSIMM
    Tailings Revegetation and Arsenic Levels in the Environment

    By D Craw

    Oceana Gold as part of their environmental strategy are looking at various methods for cost-effective revegetation of their tailings dams. Under the concept of revegetating the tailings this study loo

    Jan 1, 2006

  • SME
    Navigating Operational Hurdles in SAG Mills: Identifying and Addressing Common Challenges - SME Annual Meeting 2024

    By Kevin Erwina, Rajiv Chandramohana, Connor Meinkea

    This paper explores prevalent operational challenges encountered globally in SAG mills, including suboptimal throughput, liner wear, excessive energy consumption, and SAG mill load stability. The pape

    Feb 1, 2024

  • SAIMM
    Grade Control Blending And Selectivity For Optimal Process Performance At The Skorpion Zinc Mine, Namibia

    By G B. Gnoinski

    The Skorpion Zinc Mine and Refinery is situated approximately 25 km north of Rosh Pinah, south-western Namibia. The supergene zinc oxide deposit at Skorpion is hosted in a volcano-sedimentary success

    Jan 1, 2007

  • AUSIMM
    Study on Mineral Processing for a Cassiterite Ore in Southwest China

    Study on Mineral Processing for a Cassiterite Ore in Southwest China

    Sep 13, 2010

  • SME
    The Efects of Rock Mass Strength and Joint Orientation on Pillar Stability in Underground Coal Mines

    By S. M. Hossaini, M. Ataei, H. Moosavi

    The abstract highlights the importance of pillar stability in underground coal mines and the influence of rock mass strength and joint orientation on pillar behavior. The study employs numerical model

    Apr 4, 2022

  • CIM
    Mine Cars of Canada

    By G. C. Lipsyy

    ALL mineral production? of Can11.da is transported in a mine car at some stage during its extraction. There are as many types and varieties of mine cars as there are of mines. Many of the cars in use

    Jan 1, 1945

  • SAIMM
    Froth zone design optimisation – the key to enhancing recovery in large flotation cells, P.R. Brito-Parada, D. Mesa, J. Karvonen, R. Grau, D. Davoise, and A. López

    By D. Mesa, J. Karvonenb, A. López, P. R. Brito-Parada, R. Grau, D. Davoise

    The froth zone in flotation cells plays an important role in determining metallurgical performance. This is even more critical as cell sizes increase, since larger bursting surface areas can easily re

    Jan 1, 2020

  • AIME
    Crushing Practice at Ajo

    By David Cole

    THE New Cornelia Copper Co. is mining and treating a 'monzonite " porphyry" copper deposit that is all hard rock. The oxidized surface shell, which constitutes the leachable part of the orebody,

    Jan 1, 1925

  • NIOSH
    RI 7271 Vapor Pressures Of Liquid Titanium (2,008° To 2,379° K) And Liquid Platinum (2,045° To 2,442° K)

    By R. K. Koch

    The vapor pressures of liquid titanium and liquid platinum were studied under the Bureau of Mines program for the determination of thermochemical data on the transition elements. Beating was done in a

    Jan 1, 1969

  • AIME
    Two-Stage Program Boosts Pima To 30,000 TPD

    By George A. Komadina

    From its modest beginning in 1957 with one mill grinding section handling 3000 tpd Pima has steadily expanded. In July 1966, work was completed that allowed the concentrator to treat in excess of 18,0

    Jan 11, 1967

  • SME
    Pebbles Mills

    By B. S. Crocker

    Introduction Pebble mill grinding can be defined as wet or dry grinding in a tumbling mill with pebbles used as grinding media instead of metal balls. To clarify the terminology, which may differ i

    Jan 1, 1985

  • AUSIMM
    Optimisation Challenges in Underground Mine Planning and Design

    Underground mine planning is characterised by a series of designs, starting with prefeasibility and culminating in operational. Information on the mineralisation and geotechnical conditions is availab

    Dec 6, 2010

  • AUSIMM
    The Application of AS 61508 to Road Tunnel Fire and Life Safety Systems

    By M Taylor

    The Project Specification and Technical Requirements documents associated with several recent large road tunnel projects within Australia have specified the application of AS/IEC 61508 – FunctionalSaf

    Mar 8, 2011

  • NIOSH
    IC 7680 Methods And Costs Of Sinking A Shaft Through A Fractured, Water-Bearing Formation At Friedensville. Pa, - Introduction And Summary

    By Warren Hastings

    This paper describes the methods and costs, in units of labor end materials, of sinking a 7 compartment vertical shaft 1,261 feet through a fractured, water-saturated formation. The shaft, designed fo

    Jan 1, 1954