Design And Construction Of The Sutong Bridge FoundationsBy Robert B. Bittner
The Sutong Bridge across the lower Yangtze River in China will have, when completed, the longest span (1,088 m) and the highest towers (306 m) of any cable stayed span in the world. The foundations fo
Jan 1, 2005
-
Comparison Of Static Pile Analyses And Load Test ResultsBy Alan B. Wagner
Data from seven instrumented pile load tests in Milwaukee, Wisconsin and two other instrumented load tests reported in the literature, one in Evanston, Illinois and one in Houston, Texas were reviewed
Jan 1, 1991
-
Long-Term Performance Of Wind Turbine Foundations Through Numerical ModelingBy Spencer Ness, Yazen Khasawneh, William Tjaden, Mohammad Nassim
The evaluation of long-term performance of the wind turbine structures is essential in lowering the Levelized Cost of Electricity (LCOE) from wind sources. The required maintenance of the wind turbine
Oct 1, 2022
-
Disconnected Piled Raft Foundations Performance (DCPRF) With CushionBy Saeed Salehi Malekshah
In hybrid foundation system or piled raft foundation (PRF), the raft has adequate bearing capacity and piles are usually required to ensure overall stability of foundation and also to act as settlemen
Jan 1, 2011
-
Load Testing Of Deep Foundations Using The Osterberg Load CellBy David E. Thompson
This paper describes the full-scale field load testing of three deep foundation units using the Osterberg Load Cell. The load tests were completed on three separate projects, two in Massachusetts and
Jan 1, 1989
-
Systematic Evaluation of Driving Criteria and Performance of Tapered Piles in Glacial SandBy Terrence M. Carroll, Chu E. Ho, Dimitrios Niarchos
"Construction of the new extension to Terminal 4 at John F Kennedy International Airport in Queens, New York involved the application of tapered piles for foundation support. Initial design based on p
Jan 1, 2017
-
Augered Cast-In-Place (ACIP) And Drilled Displacement (DD) Pile Quality Control ? IntroductionBy Rudolph P. Frizzi
Quality control is essential for augered cast-in-place (ACIP) piles (also known as continuous flight auger (CFA) piles outside the United States) and drilled displacement (DD) piles since the pile is
Jan 1, 2004
-
Displacement And Pore Pressure Monitoring During Installation Of Drilled Displacement PilesBy Lisa M. Splitter
Drilled displacement piles were constructed as the foundation for a proposed 10-story building in San Francisco, California. At the study location, the stratigraphy consists of 14 to 21 feet of fill
Jan 1, 2009
-
Evaluation Of Design Methods For Tieback Retaining Walls In Seattle - IntroductionBy John P. Turner
The behavior of tieback retaining walls depends on many factors, including soil properties, groundwater conditions, construction sequence, spacing and stiffness of tiebacks and soldier piles, tieback
Jan 1, 1990
-
Caisson Design And Construction Challenges On The New Tiger Stadium Project - SummaryBy Fritz J. Klingler
From site demolition, to design, to construction, Detroit's new Tiger Stadium project is required to be completed within a short 2 ½ years from award of the design-build contract. Such extreme sc
Jan 1, 1999
-
United States Capitol Visitor Center - Drilled Shafts, Utility Conflicts, And CommunicationBy Giovanni A. Bonita
The United States Capitol Visitor Center (USCVC) is one of the largest underground structures ever constructed in the Washington, DC, metropolitan area. The 600,000 ft2 (55,750 m2) structure is entir
Jan 1, 2006
-
Drilled Pile Design and Installation Challenges in an Urban EnvironmentBy Satyajit Vaidya, Rudolph Frizzi, Luis Berroteran
This paper presents design and construction challenges associated with a high-capacity rock-socketed drilled pile foundation system for a 60-story building recently constructed in an urban environment
Jan 1, 2018
-
Helical Pile-to-Pile Cap Connections Subjected To Uplift Forces: Improving Future PracticeBy Serhan Guner, Sundar Chiluwal
Although significant research has been conducted on helical piles, there is a lack of research and official design provisions on the helical pile-to-pile cap connections. These connections may govern
Jan 1, 2019
-
Design And Preliminary Investigations For Deep Foundations Of The Charleroi Locks River Wall Project, Monessen, PennsylvaniaBy Brian H. Greene
The U.S. Army Corps of Engineers, Pittsburgh District, is in the final phases of modernizing the locks and dams on the Monongahela River. One facet of this modernization is to replace the existing Lo
Jan 1, 2006
-
Reducing Construction Interference when Implementing Geotechnical Instrumentation and Monitoring in Urban Excavation ProjectsBy Martin B. Hudson, Daniel Brescia, Zhangwei Ning
Due to the complexity and sensitivity of surrounding environments, instrumentation and monitoring (I&M) is critical for many urban deep excavations. The objects to be monitored include shoring bulkhea
Jan 1, 2018
-
Augered Cast-In-Place Piles Deep Foundations Institute (DFI) 1988 Annual Meeting - Ritz-Carlton Hotel In Atlanta (Buckhead), GeorgiaBy James J. Neate
The augered cast-in-place pile system came into use in the late 1940's where various techniques were tried using pressure grouting methods. In the early development stages some piles were install
Jan 1, 1988
-
Ground Freezing For Shoring Of Excavations - A Case History: 1405/SR522 Vault NW-6By Daniel Mageau
Ground freezing has been used for over 100 years to provide shoring and ground water cutoffs for hundreds of projects worldwide, including drilled shafts, tunnels and cofferdams. Typically, these case
Jan 1, 1998
-
Recent Advances In Large Diameter Diaphragm Wall ShaftsBy Benoit Virollet
Over the last 10 years the diameter of unbraced, unlined and unanchored circular shafts has grown dramatically in many parts of the world. This progress has taken place through improvements in: constr
Jan 1, 2006
-
Installation Of Augerpiles In Low Headroom And Restricted Access ConditionsBy Jim Steding
L.G. Barcus and Sons, Inc. recently completed a three-phase project for the expansion of Presbyterian Hospital in Albuquerque, New Mexico for McCarthy Construction Co., the Construction Manager for th
Jan 1, 2003
-
Piled Raft Design For High Rise Buildings In East London, UKBy D. P. Nicholson
The current phase of office development at Canary Wharf in the London Docklands includes twelve multi-storey buildings varying from eighteen to forty stories in height. The area of Canary Wharf South
Jan 1, 2002