    Comparative Analysis Of Longwall Gateroad Designs In Four Deep, Bump-Prone Western U.S. Coal Mines

    By Matthew J. DeMarco

    Research personnel at the U.S. Bureau of Mines have conducted longwall gate stability studies at four western U.S. mines attempting to employ yield pillars for improved ground conditions. Located in t

    Jan 1, 1993

  • SME-ICGCM
    Time-dependent Behavior of Immediate Weak Floor Strata from an Illinois Coal Mines

    By Y. P. Chugh

    The paper discusses laboratory and field studies to analyze time-dependent deformation behavior of immediate weak floor strata in an Illinois coal mine. In the laboratory, core samples of the immediat

    Jan 1, 1987

  • SME-ICGCM
    The Use of NDT Methods to Determine the Condition of Rockbolt Support During the Recovery of a Previously Flooded Coal Mine Roadway at Thoresby Colliery

    By Brian Clifford

    Thoresby Colliery is in the process of recovering an old roadway that was flooded following the closure of an adjacent mine. The aim is to re-use the roadway as a gate road for a longwall retreat pane

    Jan 1, 2002

  • SME-ICGCM
    Design, Monitoring And Evaluation Of A Pre-Driven Longwall Recovery Room

    By Tom Wynne

    In order to shorten the time required and improve safety for a longwall face move, a 36-ft wide longwall recovery room was predriven. The room was supported with specialty bolts, trusses and concre

    Jan 1, 1993

  • SME-ICGCM
    Intersection Stability and Tensioned Bolting

    By Yunqing Zhang

    Roof failure occurs much more frequently at intersections than entries and crosscuts. Using a commercial finite element package, four-way and three-way intersections reinforced with the tensioned bolt

    Jan 1, 2003

  • SME-ICGCM
    State Of The Art Testing Of Powered Roof Supports

    By Robert C. Garson

    The Mine Roof Simulator at the DOE'S Mining Equipment Test Facility is described. Its use in the research and development on the behavior and response of longwall roof supports to simulated mine

    Jan 1, 1982

  • SME-ICGCM
    Determining Horizontal Stress Direction Using The Stress Mapping Technique

    By T. P. Mucho

    Mine roof failure due to excessive horizontal stress has been recognized as a major cause of hazardous roof conditions in some mines. Stress measurements gathered by the U.S. Bureau of Mines (USBM) at

    Jan 1, 1994

  • SME-ICGCM
    Stability Evaluation Of Alternative Designs Of Drift-And-Fill Stoping In Zhaoyuan Gold Mine, P. R. China

    By Xianming Zhou

    Mining economics is such that too conservative in safety will result in a considerable penalty in mining cost. However, initial planning and design of a mining project often must be done without compl

    Jan 1, 1989

  • SME-ICGCM
    International Experience with Longwall Mining into Pre-driven Rooms (7f55d3bb-2127-4b96-860d-e3684bbd8397)

    By David Oyler

    Unusual circumstances may require that a longwall retreat into or through a previously driven room. The operation can be completed successfully, but there have been a number of spectacular failures wh

    Jan 1, 1998

  • SME-ICGCM
    Integrity Factor Approach to Assess the Stability of Room-and-Pillar Mines

    By Kanaan Hanna

    The integrity factor approach was developed by the Bureau of nines to assess the stability of mine pillars and has been applied primarily to longwall chain pillars. Recently this approach was applied

    Jan 1, 1988

  • SME-ICGCM
    Long-term Subsidence Over Longwall Chain Pillar Systems and Its Effects on Surface Structures

    By Yi You

    A research has been conducted to study the long-term subsidence and its possible effects on surface structures In this research, the surface movements in areas when potential for developing long-term

    Jan 1, 1997

  • SME-ICGCM
    Applications Of Reflection Seismics To Mapping Coal Seam Structure And Discontinuities

    By T. L. Dobecki

    As a means of demonstrating the effectiveness of reflection seismology in determining continuity of coal seams, three U. S. field projects are reviewed. The three projects involve coals of varied thic

    Jan 1, 1981

  • SME-ICGCM
    Cutable and Variable Yield Cement Cribbing Successfully Support 84 Mine Longwall Cut Through Entries

    By William Bookshar

    The development of increasingly more sophisticated and powerful retreat longwall equipment has led to ever wider and longer panels. To maximize gateroad development efficiency, provide for effective f

    Jan 1, 1998

  • SME-ICGCM
    Controlled Thrust And Torque Placement Of Mechanical Anchor Bolts And Their Relationship To Improved Roof Control

    By Anil Mahyera

    Under contract to the Bureau of Mines, a roofbolting machine has been developed which will: control torque on the bolthead to within 4 percent of a set point, control thrust to a low level (150 lbf),

    Jan 1, 1981

  • SME-ICGCM
    Mine Panel Collapse - Two Case Studies

    By Hanjie Chen

    A mine panel collapse may occur when pillar sizes are too small or the surrounding rock strata (roof or floor) yields. After a small pillar fails, its loading is rapidly transferred to adjacent pillar

    Jan 1, 1999

  • SME-ICGCM
    Manifestation Of Mine Pressure And Its Relations To Overlying Strata Movements

    By Z. C. Song

    [THIS PAPER WAS TRANSLATED FROM CHINESE TO ENGLISH BY S. S. PENG, WEST VIRGINIA UNIVERSITY] Immediately after coal extraction, the pressure that causes the movement of the surrounding strata is c

    Jan 1, 1982

  • SME-ICGCM
    Variation In The Load Transfer Of Fully Encapsulated Rockbolts

    By Paul Hagan

    A diverse range of rockbolt designs and resin anchors are available for use in underground mines. Despite their wide spread use, the factors that affect the performance a rockbolt is not fully underst

    Jan 1, 2004

  • SME-ICGCM
    A Computer Simulation Of Breakage Of The Main Roof In Longwall Mining

    By Deren Zhu

    Based on the results of field observation and physical model analyses, a computer simulation method, FEAEBP, has been developed for simulating the breakage of the main roof by considering it as a Kirc

    Jan 1, 1988

  • SME-ICGCM
    Status Of Longwall Research In CSIRO

    By Michael Kelly

    Current research in longwall mining in CSIRO Exploration & Mining is focused within five major projects and several minor projects. The major projects are: 1 3D Aspects of Longwall Geomechanics. Th

    Jan 1, 2001

  • SME-ICGCM
    Three-Dimensional Simulations Of The Roof Behavior In Coal Room And Pillar Panels

    By Andre Vervoort

    The roof in coal room and pillar panels is normally stratified and can be thought of as beams or plates supported by the pillar sides in the roadways and by pillar corners in the intersections Undergr

    Jan 1, 2000