Search Documents

Sort by

  • DFI
    Construction Of Long Tubular Column Foundations Under Deep Water ? Synopsis

    By C. L. Liao

    The chief experiences for constructing deep tubular columns foundation under deep water are as follows: 1. P.C. tubular columns were sunk inside the caisson. 2. P.O. tubular columns of 3.6 M. diameter

    Jan 1, 2010

  • SME
    Construction Of Longueuil "Centre" 4.0 M Diameter Interceptor In The Montreal Area

    By Rudy Scarabelli, John R. Wagner

    At one time explosives were the only economical means of rock tunnel excavation. Except in relatively long tunnels in the right rock explosives are still the cheapest means of rock excavation where th

    Jan 1, 1987

  • SME
    Construction Of Louisville Water Company?s Riverbank Filtration Tunnel And Pump Station Project

    By S. Holtermann

    Through the process of Riverbank Filtration (RBF), the Louisville Water Company plans to obtain a higher quality source of water for their B.E. Payne Water Treatment Plant (WTP) by means of four colle

  • SME
    Construction of Nine Shafts for the Manhattan Section of the New York City Water Tunnel No. 3

    By Yifan Ding, Shemek Oginski, Patrick Finn

    The Manhattan section of the New York Water Tunnel No. 3 constructed by the Schiavone/Shea/Frontier-Kemper Joint Venture is a $668 million project. The contract includes a tunnel drive of 8.85 km (29,

    Jan 1, 2007

  • SAIMM
    Construction Of Permanent Intruded Plugs At South Deep Gold Mine

    By D. A. Bruce

    The paper describes the construction of 5 plugs to resist high water heads at depth within the South Deep Gold Mine, Randfontein, South Africa. A total of 20 segments were involved to create these plu

    Jan 1, 2006

  • DFI
    Construction Of Pile Foundation For Railway Viaducts

    By M. D. Khattar

    The paper describes the salient construction features of the Pile foundation work for the Railway viaducts in Algeria. Six viaducts were constructed for execution of the Railway line between Aintemouc

    Jan 1, 1989

  • SME
    Construction of Portals for Adits at Stillwater Mining Company’s East Boulder Project

    By Hendrick A. D. Kirsten, A. Clayr Alexander

    Stillwater Mining Company is currently developing a second underground palladium and platinum mine approximately 21 km (13 miles) west of their existing Nye operation in the Bear tooth Mountains of so

    Jan 1, 2001

  • CIM
    Construction of prime coking coal washeries in India

    By Bali. D. D., S. Chattopadhyay

    "The planning and construction of prime coking coal beneficiation plants in the nationalized mines in India are reviewed. Flow schemes, construction practice, materials consumption, and costs are deta

    Jan 1, 1986

  • AUSIMM
    Construction of Reinforced Concrete Chimney at Yallourn Briquetting Works

    The principal dirnensions of the chimney were fixed as follows: Height from formation to coping, 328 ft. 8 in.; inside diameter concrete shell, 13 ft. Gin.; inside diameter of the 4~-in. brick lining.

    Jan 1, 1924

  • SME
    Construction Of Shin-Kanmon Tunnel On Sanyo Shinkansen

    By Kazuo Magata, Hirohiko Fujita, Masazumi Tashiro, Yoshiaki Sato, Yoshio Shinoda

    The Shinkansen of the Japanese National Railways (JNR) presently in operation between Tokyo and Hakata, approximately 1,000 km, was constructed at three stages: between Tokyo and Shin-Osaka opening in

    Jan 1, 1976

  • SME
    Construction of the Big Walnut Augmentation/Rickenbacker Interceptor Tunnel (BWARI, Part 1) —Columbus, Ohio

    By Glen D. Frank, Jeremy P. Theys, Mina M. Shinouda, Gary W. Gilbert

    PURPOSE OF THE PROJECT The Big Walnut Augmentation Rickenbacker Interceptor project began in 1995with the preparation of the Scope of Services for the design of the Rickenbacker Interceptor, with

    Jan 1, 2007

  • AUSIMM
    Construction of the Brunswick Street Rail Tunnels

    The paper, one of two papers on the Queensland Railways Brunswick Street tunnels presented at the VIII Australian Tunnelling conference, describes documentation, tendering and construction aspects.Ten

    Jan 1, 1993

  • SME
    Construction of the C710 Beacon Hill Station Using SEM in Seattle— “Every Chapter in the Book…”

    By Zephaniah Varley, Satoshi Akai, Richard Sage, Steve Redmond, Mike Murray, Rohit Shetty, Gerald Skalla

    One would be hard pressed to find another project as complex as this one given its configuration, the variety of issues to address and the required construction techniques. Contract C710 is currently

    Jan 1, 2007

  • SME
    Construction of the Combined Sewage Overflow Tunnel for the City of Fall River

    By Shemek Oginski

    The 5 km (16,194 lf) of 6.1m (20 ft) diameter TBM driven tunnel built by the J.F.Shea Co. will serve as sewage overflow storage. The TBM tunnel and four connecting tunnels excavated by drill and blast

    Jan 1, 2005

  • SME
    Construction Of The East Side Access Manhattan Tunnels

    By Don Hickey

    The MTA in conjunction with LIRR, are in the process of expanding one of the largest commuter railroads in the country, with over 260,000 passengers a day. The LIRR, which provides 700 passenger train

  • SME
    Construction of the Lewis Street CSO Tunnel, Nashville, Tennessee

    By Patrick J. Doig

    The Lewis Street CSO Tunnel is an important element in the efforts of the Metropolitan Government of Nashville and Davidson County (Metro) to improve the treatment of waste-water in the area. The t

    Jan 1, 1997

  • SME
    Construction Of The MCUA Tunnel And Force Mains Under The Raritan River, New Jersey: A Case History

    By Bob Rautenberg

    The Construction of Tunnel and Edison Force Mains contract involves the installation of two new force mains to provide a redundant means for sewage conveyance from Middlesex County Utility Authority?s

  • SME
    Construction of the N20 To N25 Tunnel (basic) Segment of the Superconducting Supercollider Project]

    By Joseph A. Whitchurch

    The N20 to N25 Tunnel (basic) segment was the second tunnel contract awarded for construction by The PB/MK Team. This project embodied 3.9 km (2.4 miles) of tunnel and was located within the northwest

    Jan 1, 1995

  • SME
    Construction of the NATM Tunnel at San Diego State University

    By Justin Brown, Michael Kobler, Dave Ragland, Bob Shufflebotham

    PROJECT OVERVIEW As the sun-bronzed San Diego students strolled casually to class, mining crews from Atkinson Construction were working only 9 meters below the surface. The330 meter long, 11.3 met

    Jan 1, 2003

  • SME
    Construction Of The North Dorchester BAY Cso Storage Tunnel In Boston

    By J. Davies

    This paper describes the successful management and construction of the 5.18 m (17 ft) diameter, segmentally lined, North Dorchester Bay CSO storage tunnel in Boston, MA. This 3,300 m (10,830 ft) long