    Tied-Back Micropile Walls In Landslide Repair

    By Kevin W. Cargill

    In September 2004, Hurricanes Frances and Ivan caused the Pigeon River in western North Carolina to flood. This flooding eroded the embankment below Interstate 40 (I-40) and sent one of the eastbound

    Jan 1, 2006

  • DFI
    Large Diameter Machine Bored Piles In Australia

    By W. J. Kingwell

    Where the equipment, technique and materials are available for the construction of large diameter rock socketted piles, this is frequently the most economical and environmentally acceptable method of

    Jan 1, 1989

  • DFI
    Analysis Of Strain-Dependent Concrete Modulus From Mass Instrumented Test Pile Samples

    By Lee Sieng Kai

    This paper presents the result of the analysis of strain-dependent concrete modulus from full-scale static axial compression load tests conducted on more than 200 instrumented cast-in-place barrettes

    Jan 1, 2006

  • DFI
    Production And Testing Of 600 Reinforced-Concrete Piles For The Central Bank Of Iraq

    By H. Meseck

    The new building of the Central Bank of Iraq in Baghdad was footed in difficult underground conditions on more than 600 reinforced concrete driven piles, with cross-sectional diameters of 45 x 45 cm a

    Jan 1, 1989

  • DFI
    Combined Loading Tests On Large Diameter Piles

    By A. Lyndon

    Combined loading tests are described to three 1.2m diameter cast-in-place bored piles, 12m long, formed through cohesionless material into stiff sandy clay. The maximum loading conditions imposed at t

    Jan 1, 1989

  • DFI
    A Case Study of Wet Soil Mixing for Bearing Capacity Improvement in Turkey

    By Arash Maghsoudloo, Asli Can

    "Abstract This paper presents a ground improvement implementation case under a raft foundation of a local hospital. The selected ground improvement method is Wet Soil Mixing (WSM) technique. Soil mixi

    Jan 1, 2014

  • DFI
    Contact Pressure Characteristics Beneath Deep Foundation Of Beijing International Hotel ? Synopsis

    By X. L. Huang

    This paper deals with the experimental and theoretic study of the contact pressure beneath the deep foundation of Beijing International Hotel, The experiments have been carried out in project and in m

    Jan 1, 2010

  • DFI
    Large Diameter Shafts - Youghiogheny Reservoir Bridge

    By Paul J. Lewis

    Estimation of the axial side shear resistance of drilled shaft rock sockets is directly related to the unconfined compressive strength of the bedrock. Commonly, the mean unconfined compressive strengt

    Jan 1, 2005

  • DFI
    Laboratory Validation Of In-Situ Tests - 1. Introduction

    This paper summarizes seven years of Italian ex­perience with the use of large calibration chambers for the calibration, under closely controlled stress and strain conditions, of some in situ testing

    Jan 1, 1987

  • DFI
    I-880 Replacement Project (Cypress Freeway) Large Diameter Driven Pipe Pile Foundations Test Program And Construction Test Pile Program - Indicator Pile Test Program - Field Work

    By Darrell L. Beddard

    Pile driving started October 29, 1993 and was completed on January 27, 1994. Field work included driving piling from ground surface at one site and at or near proposed footing elevations for the remai

    Jan 1, 1996

  • DFI
    The Effect Of Vertical Pile Loading On Subsequent Lateral Behaviour

    By A. Lyndon

    Vertical and lateral load tests were carried out on two 13 m deep bored cast-in-place instrumented piles, socketed into weathered sandstone. The first pile, 1200 mm in diameter, was loaded vertically

    Jan 1, 1989

  • DFI
    Excavation Support At Historic Buildings In An Urban Environment - A Case Study

    By Tony Mazzo

    It has often been said by consulting engineers that foundation contractors are in the business of taking risks. One would agree that the mere fact a foundation project can be budgeted, planned, engine

    Jan 1, 2003

  • DFI
    Caltrans Bridge Seismic Design/Retrofit Criteria ? Synopsis

    By Brian Maroney

    In this paper an overview of the California Department of Transportation's (CALTRANS) bridge design criteria is presented. Special emphasis is focused upon seismic design and retrofit criteria. T

    Jan 1, 1993

  • DFI
    High Risk Control For Piling And Deep Foundations - A Systematic Approach

    By Martin van Staveren

    In today's rapid changing construction world, the business pressures on piling and deep foundations reach sky-high levels. Ever increasing complexity of construction projects do severely contribu

    Jan 1, 2006

  • DFI
    Kirkpatrick Street Pump Station Addition Excavation: Small Project, Big Twist

    By James P. Stewart

    This case history describes the engineering design and construction for the Contractor of a 35-ft-deep excavation for an 800-square-foot addition to an existing sewage pump station. The site posed une

    Jan 1, 2003

  • DFI
    2 Recent Technological Developments In Deep Foundations Without Soil Excavation - Recent Technological Developments In Deep Foundations Without Soil Excavation - Brief Review Of Papers To Session 2

    By Bengt H. Fellenius

    Session 2, Deep Foundation without Soil Excavation, has attracted no fewer than 22 papers dealing with subjects from soil improvement by grouting, injection, and deep mixing techniques through vibrofl

    Jan 1, 1994

  • DFI
    Vibration-Free Driven Tubular-Piles

    By S. Doombos

    To convert the railway-bridge across the Oude Maas between Dordrecht and Zwijndrecht into a vertical lifting bridge, a drastic adaptation of the existing piers is necessary. Extra piles have to be pla

    Jan 1, 1989

  • DFI
    Recent Advances In Soil Nailed Earth Retention

    By Tom A. Armour

    Different variations of soil nailing techniques have been used in the United States since the late 1970's. Such techniques owe their origins to French developments, which began in the early 1970&

    Jan 1, 2003

  • DFI
    O Street Anchored Precast Lagging And Soldier Pile Retaining Wall

    By John Wise

    Significant movement to an existing slurry wall which serves as a retaining wall on 'O' Street in Southeast Washington, D.C. initiated the Department of Public Works for the District of Colu

    Jan 1, 2003

  • DFI
    Tied-Down Boat Section Construction

    By Romano J. Micciche

    One of the largest scale uses of a multiple, high-strength steel bar tiedown system is described. Tiedowns were installed to resist hydrostatic uplift forces acting on a section of the Interstate High