The Commissioning of No. 5 Blast Furnace at Port Kembla
    
    - Organization:
 - The Australasian Institute of Mining and Metallurgy
 - Pages:
 - 14
 - File Size:
 - 495 KB
 - Publication Date:
 - Jan 1, 1976
 
Abstract
Present capacity for molten iron production at Port Kembla is an average of 13 000 t/day  from five blast furnaces. The most recently  installed blast furnace, No.5, was commissioned  in March 1972 with a design capacity of 4 500  t/day. For the first reline currently scheduled  for 1977, plans are being finalized.for  significant modifications and uprating of  capacity. Achievement of the initial design capacity  from No.5 blast furnace on a sustained basis was  not realised until the third year of operation.  Although the furnace is only 42% larger than  No.4 blast furnace on an inner volume basis, the  more stringent raw materials, operation and  maintenance requirements of the larger furnace  and more complex equipment have been found to be  much more critical than anticipated in the  planning stages. These problems have also been  experienced by many other companies who have  recently installed large new blast furnaces. Some of the principal problem areas are  described together with measures taken to over- come the difficulties. The problem areas  include the failure of'the shower cooled bosh,  failure of the upper shaft brickwork, sludge
Citation
APA: (1976) The Commissioning of No. 5 Blast Furnace at Port Kembla
MLA: The Commissioning of No. 5 Blast Furnace at Port Kembla. The Australasian Institute of Mining and Metallurgy, 1976.