Design, Construction, Commissioning And Operating Of the Elura Concentrator
    
    - Organization:
 - The Australasian Institute of Mining and Metallurgy
 - Pages:
 - 10
 - File Size:
 - 363 KB
 - Publication Date:
 - Jan 1, 1983
 
Abstract
This paper describes major events in the  design, construction, camtissioning and  operation of the Elura concentrator. It  covers the period fran September, 1974 when  laboratory testwork on drill core cotmenced  to March, 1983 when the concentrator  catmenced operation on run of mine ore  following successful completion of initial  ccnmissioning tests. The concentrator was designed to treat  1.1 million tonnes of lead-zinc-silver ore  per year with a plant availability of 89 per  cent. This treatment rate has been achieved  for test periods.
Citation
APA: (1983) Design, Construction, Commissioning And Operating Of the Elura Concentrator
MLA: Design, Construction, Commissioning And Operating Of the Elura Concentrator. The Australasian Institute of Mining and Metallurgy, 1983.