Design, Construction, Commissioning And Operating Of the Elura Concentrator

- Organization:
- The Australasian Institute of Mining and Metallurgy
- Pages:
- 10
- File Size:
- 363 KB
- Publication Date:
- Jan 1, 1983
Abstract
This paper describes major events in the design, construction, camtissioning and operation of the Elura concentrator. It covers the period fran September, 1974 when laboratory testwork on drill core cotmenced to March, 1983 when the concentrator catmenced operation on run of mine ore following successful completion of initial ccnmissioning tests. The concentrator was designed to treat 1.1 million tonnes of lead-zinc-silver ore per year with a plant availability of 89 per cent. This treatment rate has been achieved for test periods.
Citation
APA:
(1983) Design, Construction, Commissioning And Operating Of the Elura ConcentratorMLA: Design, Construction, Commissioning And Operating Of the Elura Concentrator. The Australasian Institute of Mining and Metallurgy, 1983.